Two distinct, but related cases are of relevance in showing the genesis of this application.
The first relates to the respondent seeking to enforce a contract of works. The second relates to the applicant’s claim to enforce an agreement to arbitrate (as per the contract agreement). In this application before the High Court, the applicant sought to have the former case stayed, pending the final determination of the latter.
The applicant claimed that he sought the order to stay the suit as there was an agreement to arbitrate; proceeding with the respondent’s claim would be nugatory. The respondent resisted this application on the basis of procedural correctness.
This court determined that the issue was to verify whether this court had jurisdiction to entertain an application for stay of the respondent’s case, in view of the notice of appeal that was instituted by the applicant.
It was held that this court lacks jurisdiction over the latter case; it is the Court of Appeal which holds jurisdiction. Therefore, the matter was dismissed in its entirety.